File #: CONS 19-590   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 9/10/2019 Final action:
Subject: Adopt a Resolution Approving Addendum Nos. 1 and 2 and Award a Construction Contract to Con-Quest Contractors, Inc. for the Recycled Water Customer Onsite Conversions Project, Project No. 07507
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution

DATE:      September 10, 2019

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works                     

 

SUBJECT                     

 

Title                      

Adopt a Resolution Approving Addendum Nos. 1 and 2 and Award a Construction Contract to Con-Quest Contractors, Inc. for the Recycled Water Customer Onsite Conversions Project, Project No. 07507                 

                                            

End
RECOMMENDATION

Recommendation

 

That Council adopts a resolution (Attachment II) approving Addendum Nos. 1 and 2 and awarding a contract to Con-Quest Contractors, Inc. to construct the recycled water customer onsite conversions, in an amount not to exceed $1,826,600.

End

 

SUMMARY

 

The City’s Recycled Water Project consists of constructing a treatment facility, storage tank, and pump station at the City’s Water Pollution Control Facility (WPCF) and installing distribution pipelines and customer connections to deliver recycled water to customers for irrigation and industrial uses. The project is being constructed under multiple contracts. On July 16, 2019, Council approved the plans and specifications for Recycled Water Customer Onsite Conversions and called for bids to be received by August 20, 2019. Only one bid was received from Con-Quest Contractors, Inc.  Staff is requesting Council approval to award the construction contract to Con-Quest Contractors, Inc., in an amount not to exceed $1,826,600, which includes the bid of $1,739,600 and an $87,000 administrative change order contingency for unforeseen changes during construction.

 

ATTACHMENTS

Attachment I                                           Staff Report

Attachment II                      Resolution