DATE: July 7, 2020
TO: Mayor and City Council
FROM: Director of Public Works
SUBJECT
Title
Adopt a Resolution Approving Addenda Nos. 1 through
6, Authorizing the Substitution of Subcontractors, Waiving Errors Related to Subcontractor's DIR/Contractor's Numbers and Awarding a Contract to S. J. Amoroso Construction for the
Fire Station 6 and
Fire Training Center Project, Project Nos. 07481 and 07482 in the Amount of $52,397,000
End
RECOMMENDATION
Recommendation
That Council adopts a resolution (Attachment II) approving Addenda Nos. 1 through
6, providing revisions to the plans and specifications and responses to clarification for the
Fire Station 6 and
Fire Training Center Project, authorizing the substitution of subcontractors, waiving errors related to subcontractor Department of Industrial Relations (DIR) registration number and contractor's license number, awarding the contract to S. J. Amoroso Construction (Amoroso) in the amount of $52,397,000, and authorizing the City Manager to spend up to $70,901,700 for the total project cost.
End
SUMMARY
In 2014, the voters of the City of Hayward (City) approved Measure C, which authorized the City to increase the sales tax rate by one-half cent for, among other things, the restoration and maintenance of City services and facilities, including
firefighting/emergency medical services. City staff and the design team have been working on completion of the design and various approvals of this project for several years. This project includes partnership with the Chabot-Las Positas Community College District (District) for the shared use of the
Fire Training Center. With the completion of the construction documents and approvals by Division of the State Architect (DSA) and Federal Aviation Administration (FAA), the project was advertised on April 3, 2020.
On June 11, 2020, the project received two bids. Both bids were under the engineer's estimate of $57,000,000. The ...
Click here for full text