File #: CONS 22-358   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 6/21/2022 Final action:
Subject: Adopt a Resolution Awarding a Contract to GSW Construction, Inc., for the Trash Capture Device Installation on Cotter Way Project No. 07675 in the Amount of $188,600, Approving $18,900 Construction Contingency Budget, and Appropriating an Additional $70,000 to the Project
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Location Map
DATE: June 21, 2022

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT

Title
Adopt a Resolution Awarding a Contract to GSW Construction, Inc., for the Trash Capture Device Installation on Cotter Way Project No. 07675 in the Amount of $188,600, Approving $18,900 Construction Contingency Budget, and Appropriating an Additional $70,000 to the Project

End
RECOMMENDATION

Recommendation
That Council adopts a (Attachment II) approving Addendum No. 1 to the specifications, which included rescheduling the pre-bid meeting for the Cotter Way Project, Project No. 07675 (Project), and awarding the construction contract to GSW Construction, Inc., (GSW) in the amount of $188,600, approving a construction contingency budget of $18,900, and approving an additional appropriation of $70,000 to the Project.

End
SUMMARY

The proposed Project would install a continuous deflective separator (CDS) unit in the existing storm drain under Cotter Way for trash capture from the stormwater system as part of the City's trash reduction mandate from the San Francisco Regional Water Quality Control Board (Water Board). The CDS unit creates a continuous swirl of stormwater to concentrate and separate trash and debris. This project would be funded by the US Environmental Protection Agency (EPA) Water Quality Improvement Fund grant awarded to the City in January 2015.

In May 2022, the City released a call for bids and received two competitive bids. Staff recommends awarding the contract to GSW Construction, Inc., in the amount of $188,600 and a contingency budget of $18,900 for a total amount not-to-exceed $207,500.

This project is categorically exempt from environmental review under Section 15301(c) of the California Environmental Quality Act (CEQA) Guidelines for the operation, repair, maintenance, or minor alteration of existing facilities.

ATTACHMENTS

Attachment I Staff Report
Attachment II Resolution
Attachment...

Click here for full text