File #: CONS 22-416   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 7/5/2022 Final action:
Subject: Adopt a Resolution Approving Addendum No. 1 and Awarding a Contract to GSW Construction, Inc., for the Willimet Way & I-880 Sanitary Sewer Main Installation Project, Project No. 07717, in an Amount of $770,218 with the Addition of $85,000 in Administrative Change Orders and Appropriating Additional Funds in an Amount of $543,675 RECOMMENDATION
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Location Map

DATE:      July 5, 2022

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works                     

 

SUBJECT

                     

Title                      

Adopt a Resolution Approving Addendum No. 1 and Awarding a Contract to GSW Construction, Inc., for the Willimet Way & I-880 Sanitary Sewer Main Installation Project, Project No. 07717, in an Amount of $770,218 with the Addition of $85,000 in Administrative Change Orders and Appropriating Additional Funds in an Amount of $543,675              

   

RECOMMENDATION

 

Recommendation

That Council adopts a resolution (Attachment II):

 

1.                     Approving Addendum No. 1, providing minor revisions to the project specifications; and awarding the construction contract to GSW Construction, Inc., (GSW) for the Willimet Way & I-880 Sanitary Sewer Main Installation Project, Project No. 07717, in an amount of $770,218 with the addition of $85,000 in administrative change orders; and

 

2.                     Appropriating additional funds in the amount of $543,675 from Sewer System Improvement Fund (Fund 612).

 

End

SUMMARY

 

The Utilities Division of the Public Works & Utilities Department replaces the City’s undersized or structurally damaged sewer mains through capital improvement projects. These projects reduce the risk of potential sanitary sewer overflows, which can cause untreated wastewater to flow into public waterways. This project will install approximately 165 linear feet of 12-inch sanitary sewer main at a new location to increase pipeline capacity and replace a damaged sewer main between Willimet Way and the Highway 92W/Interstate 880N on-ramp within California Department of Transportation’s (Caltrans) right-of-way (Attachment III). The project also includes installation of approximately 200 linear feet of new 8-inch sanitary sewer pipe and manholes and reversing the flow to drain to the new pipe location in Willimet Way.

 

On June 1, 2022, two (2) bids were received. The low bid was $770,218 which is $69,782, or approximately 8% below the Engineer’s estimate of $840,000. Staff is requesting Council’s approval of Addendum No. 1, which provided minor revisions to clarify the specifications, and awarding the contract to the lowest bidder, GSW, in the amount not-to-exceed $855,218, including Administrative Change Orders.  Furthermore, staff is requesting appropriation of additional funds in the amount of $543,675 from the Sewer System Improvement Fund (Fund 612).

 

This project is categorically exempt from environmental review under Section 15301(c) of the California Environmental Quality Act (CEQA) Guidelines for the operation, repair, maintenance, or minor alteration of existing facilities.  Additionally, the Community Workforce Agreement (CWA) requirements do not apply to this project since the project construction cost is less than $1,000,000.

 