File #: CONS 24-302   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 6/4/2024 Final action:
Subject: Adopt Resolutions Authorizing the City Manager to (1) Amend the Professional Services Agreement with Mark Thomas & Company for Extended Construction Support Services by $154,000 for a Not to-Exceed Amount of $1,780,180 and (2) Amend the Contract with Bellecci & Associates, Inc., by $72,500 for a Not-to Exceed Amount of $147,433 for the Mission Boulevard Corridor Improvements Phase 3 Project, Project No. 05287
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution Mark Thomas & Company, 3. Attachment III Resolution Bellecci & Associates, Inc.
DATE: June 4, 2024

TO: Mayor and City Council

FROM: Director of Public Works

SUBJECT
Title

Adopt Resolutions Authorizing the City Manager to (1) Amend the Professional Services Agreement with Mark Thomas & Company for Extended Construction Support Services by $154,000 for a Not to-Exceed Amount of $1,780,180 and (2) Amend the Contract with Bellecci & Associates, Inc., by $72,500 for a Not-to Exceed Amount of $147,433 for the Mission Boulevard Corridor Improvements Phase 3 Project, Project No. 05287

End
RECOMMENDATION
Recommendation

That Council adopts the attached resolutions (Attachments II, III) authorizing the City Manager to:

1. Amend the Professional Services Agreement (PSA) with Mark Thomas & Company (Mark Thomas) for extended construction support services for the Mission Boulevard Corridor Improvements Phase 3 project by $154,000 for a not-to-exceed (NTE) amount of $1,780,180;
2. Amend the Contract with Bellecci & Associates, Inc., (Bellecci) for extended construction staking services for the Mission Boulevard Corridor Improvements Phase 3 project by $72,500 for a NTE amount of $147,433.
End

SUMMARY

Construction of the Mission Boulevard Corridor Improvements Phase 3 project from A Street to Rose Street started on July 10, 2023. After the start of construction, a number of issues were encountered that now extends the estimated construction completion date to Summer of 2025.

Mark Thomas was contracted to provide final design for the project as well as construction support during construction. Mark Thomas provided construction support services when construction started and their remaining fees are nearly exhausted. Staff negotiated a fee of $154,000 with Mark Thomas & Company for additional construction support services. Construction also requires construction staking. A request for proposal for construction staking was issued and a contract was established with Bellecci. The remaining amount will al...