Legislation Details

File #: CONS 26-192   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 5/19/2026 Final action:
Subject: Adopt a Resolution Approving the Plans and Specifications and Calling for Bids for the FY24 Sewer Line Replacement Project, Project No. 07789
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III Location Map

DATE:      May 19, 2026

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution Approving the Plans and Specifications and Calling for Bids for the FY24 Sewer Line Replacement Project, Project No. 07789

 

End
RECOMMENDATION

Recommendation

 

That City Council adopts a resolution (Attachment II) approving the plans and specifications for the FY24 Sewer Line Replacement Project, Project No. 07789, and calling for construction bids to be received on June 30, 2026.

End

 

SUMMARY

 

The Utilities Division of the Department of Public Works & Utilities manages replacement of the City’s undersized or structurally damaged sewer mains through annual Capital Improvement Program (CIP) projects. The FY24 Sewer Line Replacement Project will improve the capacity and maintain the operability of the sewer collection system by replacing or rehabilitating approximately 4.68 miles of existing vitrified clay pipe (VCP) and asbestos cement pipe (ACP) ranging in diameter from 6 to 10-inch with new 8, 10, 12, 15, or 18-inch PVC or HDPE pipe. This project takes place at twenty-six locations throughout the City (Attachment III).  Approximately 2.04 miles will be replaced by traditional open-cut method, another approximately 0.77 mile will be replaced by trenchless technology used to cross under obstructions that prohibit open-cut installation, and approximately 1.87 miles will be repaired with Cured-In-Place Pipe (CIPP) lining.  Design has been completed and bid documents have been prepared. Staff is requesting City Council’s approval of the plans and specifications and calling for bids to be received on June 30, 2026.

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment II                                          Resolution

Attachment III                                          Location Map