Legislation Details

File #: CONS 26-364   
Section: Consent Status: Agenda Ready
Meeting Body: City Council
Agenda Date: 10/6/2026 Final action:
Subject: Adopt a Resolution 1) Approving Addenda Nos. 1, 2, and 3, 2) Rejecting a Bid Protest, 3) Authorizing the City Manager to Award a Contract to Columbia Electric, Inc., in the Amount of $164,500 Including Approval of Up to $20,500 in Administrative Change Orders, and 4) Appropriating Additional Funds in the Amount of $84,375 for the Tennyson Park Streetlight Project, Project No. 06973
Attachments: 1. Attachment I Staff Report, 2. Attachment II Resolution, 3. Attachment III HARD Staff Report, 4. Attachment IV Bid Protest - St. Francis Electric, 5. Attachment V Response to Bid Protest - Columbia Electric, Inc., 6. Attachment VI City Response to Bid Protest

DATE:      October 6, 2026

 

TO:           Mayor and City Council

 

FROM:     Director of Public Works

 

SUBJECT                     

Title                      

 

Adopt a Resolution 1) Approving Addenda Nos. 1, 2, and 3, 2) Rejecting a Bid Protest, 3) Authorizing the City Manager to Award a Contract to Columbia Electric, Inc., in the Amount of $164,500 Including Approval of Up to $20,500 in Administrative Change Orders, and 4) Appropriating Additional Funds in the Amount of $84,375 for the Tennyson Park Streetlight Project, Project No. 06973                                                             

 

End
RECOMMENDATION

Recommendation

 

That the City Council adopts a resolution (Attachment II):

1)                     Approving Addenda Nos. 1, 2, & 3 consisting of revisions to the plans and specifications for the Tennyson Park Streetlight Project; and

2)                     Rejecting a bid protest; and

3)                     Authorizing the City Manager to award the contract to Columbia Electric, Inc., for the Tennyson Park Streetlight Project, Project No. 06973, in the amount of $164,500 and approving $20,500 in administrative change order; and

4)                     Appropriating additional funds in the amount of $84,375 from the Gas Tax Fund (Fund 210)

End

 

SUMMARY

 

The Tennyson Park Streetlight Project calls for installation of eight streetlights around Tennyson Park; four on Panjon Street and four on Huntwood Avenue as part of the agreement with Hayward Area Recreation District (HARD) to install streetlights for the renovation of Tennyson Park Phase 2.

 

On September 1, 2026, eight (8) bids were received, three of the eight bids were under the Engineer’s Estimate. Columbia Electric, Inc., of San Leandro submitted the lowest bid in the amount of  $164,500 which is 8.6% under the Engineer’s Estimate of $180,000.

 

Staff is requesting City Council’s approval of Addenda Nos. 1, 2 and 3, which provided minor revisions to clarify the specifications and plans, rejection of a bid protest, awarding the construction contract to the lowest responsible bidder, Columbia Electric, Inc, in the amount of $164,500, and approving $20,500 in administrative change order, and appropriating additional funds in the amount of $84,375 from the Gas Tax Fund (Fund 210).

 

ATTACHMENTS

Attachment I                                          Staff Report

Attachment  II                                          Resolution

Attachment  III                     HARD Staff Report

Attachment  IV                     Bid Protest - St. Francis Electric

Attachment  V                     Response to Bid Protest - Columbia Electric

Attachment  VI                     Tennyson Park Streetlight Project - City Response to Bid Protest